Why shipping’s digital projects stall on board

The installation report says the project is complete. On board, the work of making it useful has barely begun. A former Chief Engineer and fleet manager on why digital projects stall.

Reading Time: 4 minutes

Digital projects in shipping often stall after the installation report says they are complete. A new platform goes live. Accounts are created, training is delivered and the office receives confirmation that the vessel is connected. A few weeks later, someone asks why the crew are still sending spreadsheets.

It is tempting to call this resistance to change. From the fleet manager’s chair, the question deserves a closer look.

What happens when the person expected to use the new system is also preparing for arrival, managing a defect, supervising maintenance or handing over to a relieving officer? Does the tool make that work easier? And has the office stopped asking for the information through the old channels?

Having spent 17 years at sea, including four as Chief Engineer, followed by fleet management roles ashore, I believe the difficulty often lies in the distance between how a system is introduced and how a vessel actually works.

The demonstration is only the beginning

A demonstration gives a system our full attention. The workflow is prepared, the connection is available and someone is there to explain the next step.

On a working ship, attention is divided. The person entering information may be interrupted. The connection may drop. Another task may become more urgent. A colleague unfamiliar with the system may need to take over.

These are useful conditions in which to test a product.

Before approving a fleet rollout, I would want to see a crew member complete an ordinary task without the supplier guiding every click. I would also want to know what happens when the process is interrupted.

Can the user return to an unfinished entry? Is the information available when it is needed? Can a relieving officer understand what has already been done?

A successful demonstration should lead to these questions.

The spreadsheet survives for a reason

Consider a familiar situation: a vessel records maintenance information in a new platform, then sends a spreadsheet containing the same details, followed by an email explaining the outstanding items.

The crew have learned the new system. They have also learned that the old reporting obligations remain. From their perspective, the project has added another task.

There may be a reasonable explanation. Perhaps different departments need different views. Perhaps an existing report has become part of an approval process. But resolving that duplication is a shore-management responsibility.

Every new reporting requirement should come with a review of what can be removed. If an old report must remain, the project team should be able to explain why and how the additional workload will be managed. The crew should be able to feel the benefit in their working day.

Start digital projects with the person doing the job

“The fleet needs better visibility” may be a valid business objective. It does not explain what the person onboard gains from entering the information.

A Chief Engineer may need to see whether a spare has been approved and when it will arrive. A superintendent may need a reliable view of an unresolved defect. Both needs can belong to the same workflow, provided the system is designed around them.

That requires involving users before the solution is settled. Ask officers to walk through the task as they perform it today. Where do they repeat information? What do they have to chase? Which records do they trust, and why?

These conversations can expose difficulties that a requirements document misses. They also give the project a concrete purpose: improve a task that people recognise.

Training for digital projects must survive a crew change

Initial training is a starting point. A vessel will continue changing personnel long after the launch team has moved on.

The next officer may inherit an account, a manual and an expectation to use the system correctly. If essential knowledge sits with one enthusiastic user, continuity becomes fragile.

Training should therefore be built around tasks and handovers. Short guidance on completing an inspection or closing a maintenance job can be more useful at the point of need than a lengthy presentation covering every feature.

The office also needs training. Shore staff must know where to find the information already entered, how to respond to it and which requests they should stop sending separately. Adoption is shared work.

Crews need to see digital projects respond

Entering information creates an expectation that someone will use it.

If a crew member reports a defect, what follows? Can they see that it has been reviewed? If a request is deferred, is the reason clear? When feedback identifies a problem with the system, does anyone respond?

Without that feedback, data entry can begin to feel like an administrative exercise with little connection to the work itself. Trust grows when the information produces a visible response. An approval, an explanation or a resolved issue helps demonstrate the purpose of the process.

Measure what your digital projects changed

Installation numbers, account registrations and completed training sessions tell us whether a rollout is progressing. They tell us less about whether it is helping.

For that, I would ask different questions. Has duplicate reporting reduced? Can the vessel find an answer without another email? Does the superintendent have enough information to make a decision? Are users still keeping separate records because the official system does not meet their needs?

A small pilot should make room for honest answers, including the answer that a workflow needs to change before more vessels receive it. That is valuable learning while the project is still manageable.

Digital projects are completed in daily use

Digital projects onboard need continuing attention from the office, the supplier and the people using them at sea. Responsibilities, reporting practices and handovers all need to support the change.

My starting question would be straightforward: what will become easier for the person using this tomorrow?

If we can answer that clearly, test it onboard and act on what we learn, we have a stronger basis for adoption.

A project has achieved something worthwhile when a crew member reaches for the system because it helps them complete the job.

Disclosure: the author is a Partner at VragaMarine, a maritime safety consultancy, and Vice President, Partnerships and Growth at FrontM, a maritime technology company. This article is general commentary from the author’s experience, is not about any product or company, and is not professional advice.

Written by
C/E Ankush Khanna

Ankush Khanna is a former Chief Engineer and fleet manager based in Singapore. He spent 17 years at sea, including four as Chief Engineer, followed by shore roles in ship management. His work today focuses on maritime technology, crew welfare and industry collaboration.

Views expressed are the author's own and do not represent those of their employer.