The statement of facts is the claim

On a claims desk the statement of facts is the first document opened and the last one trusted. Where it goes wrong, and how one loose phrase created a dispute.

Reading Time: 3 minutes

On a claims desk, the statement of facts is the first document opened and the last one trusted. It is the factual skeleton of a laytime or demurrage claim, and everything else in the file, the notice of readiness, the logbook, the pumping records and the agent’s messages, is tested against it. If it is vague, late or inconsistent, the other side has an opening, and the argument shifts from the delay to the paperwork.

What the claim is built from

When a claim is prepared, the person doing the laytime calculation compares the notice of readiness, the statement of facts, the port log, the pumping or loading records, the agent’s messages and the relevant charter party clauses. They are looking for the same events recorded the same way. Where they do not match, someone will ask which one is right.

Where statements of facts go wrong

Missing times. Arrival, notice tendered, berthing, hoses connected, start and stop of cargo operations, hoses disconnected and documents on board are the entries that carry the claim. A gap is an argument.

No reasons for delay. “Waiting for berth” is a time. “Waiting for berth, terminal advised berth occupied by another vessel” is evidence. The reason decides who bears the time.

Times that disagree. The statement of facts says 14:10, the logbook says 14:25, the agent’s message says 14:00. Each may be defensible. Together they are not.

Vague weather. “Rain, stopped operations” without start and end times leaves any deduction for weather open to challenge.

Signed without remarks. A clean signature means the Master agrees with every entry. If he does not, the disagreement has to be written next to the entry before it is signed.

When a generic entry becomes the argument

The entry that causes trouble is not always a missing one. Sometimes it is a short, plausible phrase that describes what the ship appeared to be doing and not why.

In one case, the statement of facts recorded that a vessel was “awaiting pilot”. In fact she was waiting for berthing instructions, because the berth was occupied. Under that charter, berthing pilotage was for owners’ account, and the charterers relied on the wording to deduct the waiting time from laytime, on the basis that the delay was the pilot’s and not the berth’s.

It took extensive correspondence and repeated challenges to establish the actual sequence of events and show that the delay was caused by the berth being unavailable. The entry was not dishonest. It was a loose description that nobody had checked, and it created an argument that would otherwise not have existed.

Two lessons follow. The reason for a delay has to be kept apart from what the ship happened to be doing during it. And an entry that is not needed to show the operational timeline is a risk with no benefit.

What the ship can do

Most of this is habit, not skill. Record each time as it happens rather than reconstructing it afterwards. Read the statement of facts before signing, and compare it with the logbook. Where an entry is wrong or incomplete, say so on the document, factually and without argument. Keep a copy of what was signed, and send it to the office promptly.

Be careful with generic or assumed descriptions such as “awaiting pilot” until the underlying reason is established, and give extra attention to any entry that could bear on a laytime exception or on the owners’ liability. Entries should be factual, precise and limited to events that matter to the timeline.

A statement of facts that records a delay accurately is not an admission. It is the start of a claim that can be proved, in either direction.

A note on the notice of readiness

Everything above depends on laytime starting when it should. A notice tendered before the ship is ready, or in the wrong place, can be invalid, and an invalid notice does not necessarily become valid when the ship later becomes ready. I covered the position outside port limits in an earlier piece, Tendering NOR outside port limits. The statement of facts is where the consequences of that decision are recorded.

Related reading: Tendering NOR outside port limits; The clause you only read when something goes wrong: the demurrage time bar.

Disclosure: the author works in commercial operations with an established tanker owner. This article is general commentary from the author’s experience and is not legal advice. Charter party terms differ, and the wording of the actual clause governs.

Written by
Capt. Nilesh Kawal

Capt. Nilesh Kawal is a seasoned maritime professional currently working in commercial operations with an established tanker owner. He brings over 17 years of seagoing experience on tanker vessels, followed by a strong shore-based career since 2012 in ship management, training, and commercial operations. His extensive sailing background has given him deep operational insight into tanker operations, safety, and compliance, which he…

Views expressed are the author's own and do not represent those of their employer.